Fill in the Blank

An electrical contractor is auditing the estimating department after missing several bid deadlines. The audit reveals that estimators are causing massive bottlenecks by requesting formal supplier pricing for every single material on the takeoff, including basic commodities. To evaluate and correct this inefficiency while still protecting the bid from price volatility on major components, the contractor must enforce a strict dollar or lead-time ________ to dictate exactly which materials justify the effort of obtaining a formal distributor quote.