Your company policy is to request formal distributor quotes for any material that exceeds a $2,000 threshold or has a lead time of 6 weeks or longer. While estimating a new restaurant project, you identify the following items on your takeoff:

  1. A custom 3-phase transformer ($1,300 cost; 10-week lead time)
  2. A crate of standard 4-inch square junction boxes ($450 cost; in stock)
  3. Specialty architectural LED pendants ($3,800 cost; 3-week lead time)
  4. 500 feet of 1/2-inch EMT conduit ($600 cost; in stock)

Which of these items must be sent to your vendor for a confirmed quote?