Multiple Choice

An electrical contractor is bidding on a project that requires 55 months of field labor. However, the vendor quote for the main electrical panel indicates a 99-month lead time. When analyzing the financial impact of this lead-time risk on the project's estimate, which of the following is the most accurate assessment of the 'hidden' cost driver?