Multiple Choice

An electrical contractor is preparing a bid for a commercial building project. The main switchgear has a supplier-quoted lead time of 56 weeks. The general contractor's schedule shows 40 weeks from notice-to-proceed to substantial completion, with liquidated damages of $1,500 per day for late completion. Review the contractor's estimating approach below and determine which element represents the most critical failure in managing lead-time risk.

The contractor's approach:

  1. Priced the switchge