Multiple Choice

An electrical contractor is bidding on a project where the client's approval process typically takes 6060 days. The material quote from the distributor is valid for only 3030 days. The contractor decides to submit a firm-price bid without any price contingencies or validity extensions, reasoning that 'securing the project is more important than worrying about a potential material price hike.' Evaluate the soundness of this business decision.