Multiple Choice

Compare these two common ways an electrical contractor might handle bid validity in a project proposal:

Option A: 'This proposal is valid for 30 days.' Option B: 'This proposal is valid for 30 days, or until the material quote expires on November 15th, whichever occurs first.'

Analyze the relationship between these two options and identify why Option B is a more robust risk management strategy.