Multiple Choice

An electrical contractor is evaluating the accuracy of their bidding process after completing a project that was estimated at $18,000 but cost $18,200 to complete. They compare two different reporting formats to decide if their bidding template needs adjustment:

  • Format A: A summary showing only that the total project was $200 over budget.
  • Format B (Estimates Versus Actuals Report): A breakdown showing that 'Labor' was $3,000 under budget, while 'Materials' were $3,200 over budget.

Evaluate which format provides the most effective evidence for improving the contractor's future bidding accuracy.