An electrical contractor reviews an Estimates Versus Actuals report for a commercial lighting project. The report shows the total project was 5% under budget. However, the 'LED Fixture' item was 15% over the estimated cost, while 'Installation Labor' was 20% under the estimated cost. The contractor decides that because the overall project was profitable, their current estimating template is accurate and requires no changes.

Evaluate the validity of the contractor's conclusion.