Multiple Choice

An electrical contractor is hired to install several designer chandeliers provided by a homeowner. To avoid conflict, the contractor agrees to use the customer's materials at their standard hourly labor rate, but requires the customer to sign a 'Delay Waiver' stating that the contractor is not financially responsible for any downtime caused by missing or incorrect parts. Based on the business principles for managing owner-provided material risks, evaluate the effectiveness of this strategy for the contractor's business.