Multiple Choice

An electrical contractor is performing a tenant build-out when the owner requests the addition of four dedicated circuits for a new server room. This change will add $1,400 to the project cost and will delay the final inspection by two days. To ensure the resulting change order is contractually valid, how should the contractor handle the schedule impact?

0

1

Updated 2026-05-09

Contributors are:

Who are from:

Tags

Electrician Business Operations

Running an Electrical Contracting Business Course

Related