An electrical contractor is performing a troubleshooting job for a commercial client under a Time-and-Material (T&M) agreement. The initial estimate range provided was $400–$600. After discovering significant hidden corrosion in the main conduit that required extra labor, the final bill comes to $1,250. The client is upset and refuses to pay the amount above the original estimate. Analyze the situation to determine which statement best identifies the procedural failure in the execution of the T&M model.