Multiple Choice

An electrical contractor is reviewing a project that is significantly over its labor budget. While the material list was 100% accurate and all parts were delivered on time, the field crew reports they are losing hours daily searching for specific connectors in bulk crates and relocating conduit bundles that were dropped in the middle of their active work zone. Which statement best analyzes the breakdown in the relationship between the material list and job-site staging in this scenario?