Multiple Choice

An electrical contractor is reviewing their monthly expenses and notices they have been billed twice for the same high-voltage transformer. After investigating the email records, the owner finds that a project manager had followed up with the supplier to 'check the status' of the delivery using only the job site name as a reference. The supplier's sales rep, unable to quickly find an existing record for that project, created a 'replacement' order to ensure the project stayed on schedule.

Analyze this administrative failure. Why would using a consistent Purchase Order (PO) reference number in the follow-up communication have most likely prevented this double-billing error?