An electrical contractor is three months into a large commercial project. Their internal records show they have spent $20,000 on materials and $15,000 on labor. They submit a progress bill for $35,000. The project owner rejects the invoice because it does not align with the 'Schedule of Values,' which shows the 'Rough-in' stage (100% complete) is valued at only $25,000. Analyze the relationship between the contractor's request and the progress billing system to determine the root cause of the rejection.