An electrical contractor receives a plan review with a comment stating that a proposed sub-panel lacks the required workspace clearance. The contractor agrees with the note and tells the field crew to move the panel two feet to the right during installation. However, the contractor does not update the permit drawings or provide a written response to the building department. During the final inspection, the project is rejected because the inspector's 'approved' plans still show the panel in the original, non-compliant location. Which statement best analyzes the breakdown in the 'Plan Review Deficiency Follow-Up' process?