Multiple Choice

You are performing a panel upgrade for a residential client. The building department's plan review identifies that your proposed wiring layout is missing required AFCI (Arc-Fault Circuit Interrupter) protection for several branch circuits. You agree that this protection is necessary. What is the most appropriate action to take in your deficiency follow-up process to ensure the project passes the field inspection?