Multiple Choice

An electrical contractor uses a composite rate for 'Single Power Point Installation' that bundles 1 outlet, 5 meters of cable, and 1 hour of labor.

Following a project, a cost analysis shows that while the number of outlets installed matched the estimate exactly:

  • The total cost of cable was 10% lower than estimated.
  • The total cost of labor was 20% higher than estimated.

Analyzing the relationship between these components, which change in project conditions most likely caused this specific outcome?

0

1