You are setting up your estimating system for the first time. You repeatedly install bathroom exhaust fans on residential jobs, and each installation consistently requires: one exhaust fan unit, a short length of flexible duct, a duct cap, wire connectors, approximately 6 metres of 2.5mm² twin-and-earth cable, and about 1.5 hours of electrician labour. You want to build a single per-unit composite rate so future estimates for this item can be completed in seconds. Which of the following represents the best-designed composite rate for this repeated work item?