An electrical contractor's written contract contains the following two provisions regarding warranty coverage:

Provision 1: 'All labor provided by the Contractor is warranted against defects in workmanship for a period of three (3) years from the date of project completion.' Provision 2: 'In the event of equipment failures caused by manufacturer defects, the Contractor’s responsibility for replacement labor is limited to the first twelve (12) months of service.'

Analyze the relationship between these two provisions to determine the contractor's liability if a high-end circuit breaker fails due to a confirmed factory defect 18 months after the project was completed.