Fill in the Blank

An estimator is evaluating supplier preassembly for a commercial lighting project. Standard boxed fixtures cost $8,000 in materials and require 100 hours of field labor to assemble and install. Pre-whipped and palletized fixtures cost $9,500 in materials but reduce the field labor to 60 hours. If the company's burdened labor rate is $50 per hour, choosing the pre-assembled option will result in a net overall cost savings of ____ dollars.