Multiple Choice

As the owner of a new electrical firm, you are designing a 'Standard Procurement Specification' to ensure your team spends as little time as possible on non-installation tasks. Which set of requirements should you create for your lighting suppliers to best utilize the principle of supplier preassembly for a large-scale commercial project?