Based on the provided 'Actual vs. Estimate' chart, an electrical contractor who relies on 'informal' material purchasing—where foremen verbally order materials without a purchase order—often discovers cost overruns only after a project is finished. Why does this informal process prevent the office from identifying these overruns while work is still in progress?