Based on the provided 'Actual vs Estimate' image, an electrical contractor realizes their actual costs are consistently higher because they have been paying for 'Job Permits' and 'Temporary Lighting' out of the general overhead account. They are debating two corrective strategies:

Strategy 1: Leave these costs in overhead but increase the standard markup on all future estimates to ensure the bills are covered. Strategy 2: Reclassify these as direct job costs and include them only in the specific bids for jobs that require them.

Evaluate which strategy is most effective for a contractor who wants to maintain a competitive edge for simple residential repairs while also bidding on complex commercial work.