Multiple Choice

Consider the following two scenarios discovered during a routine diagnostic visit:

Situation A: A homeowner has a 100-amp service and a panel that has run out of breaker spaces. Their current load calculation is 65 amps, and they have no plans to add new appliances. Situation B: A homeowner has a 100-amp service and a panel that has run out of breaker spaces. Their current load calculation is 95 amps, and they are about to install a 30-amp electric vehicle charger.

Which of the following correctly analyzes why the technical intervention for Situation A differs from Situation B?