During an internal bid review for a commercial project, your estimator suggests omitting the required cost premiums for 'after-hours only' labor to ensure your price is the lowest among competitors. He argues that by winning the contract now, you can 'work out the schedule' with the client later or find ways to save on materials to make up the difference.

Evaluate this strategy based on the standards of a professional bid review gate. Why is this reasoning fundamentally unsound for a contractor prioritizing long-term business health?