Multiple Choice

Imagine you are reviewing the results of two different pre-bid meetings for a potential electrical project. To determine which meeting provided a more 'reliable' basis for your final estimate, which summary should you judge as most effective?

Summary A: You obtained the contact information for the utility coordinator, documented the specific RFI routing procedure for the project, and recorded several document discrepancies to be submitted as formal questions for a written addendum.

Summary B: