Multiple Choice

You are bidding on a multi-building apartment complex and notice that the electrical blueprints conflict with the architectural phasing plan, and the utility tie-in points are not specified. To create a robust 'Pre-Bid Clarification Strategy' that ensures your final estimate is both accurate and contractually safe, which set of objectives should you synthesize into your meeting plan?