Referencing the provided 'Actual vs. Estimate' report, your records show 'Actual' material costs of $2,250 for the project. However, you know that $300 worth of excess wiring was returned to the supplier for a credit, but that credit was mistakenly recorded as 'General Miscellaneous Income' instead of being posted to this specific job number. What is the most significant consequence of this error when you analyze this report to prepare for your next bid?