Multiple Choice

The provided image illustrates a common outcome when material prices are underestimated during a project. If you are preparing a bid for a project that includes a $15,000 switchgear package and your internal price list is six months old, which action would most effectively prevent the 'Actual' costs from exceeding the 'Estimate' as shown in the chart?