Multiple Choice

While reviewing a project's mid-point financial report, a contractor notices that although 60% of the labor hours have been used, only 20% of the material budget has been spent. A subsequent inspection reveals a binder full of un-coded receipts for wire and fittings purchased over the last month in the foreman's truck. What does this discrepancy reveal about the project's financial status?