You are auditing a project's job costing report and notice a discrepancy: the 'Materials' category is significantly under budget, while the 'Subcontractor' category shows an unexplained cost overrun. You discover that a $12,500 invoice from your primary electrical distributor for custom switchgear was mistakenly categorized as a subcontractor payment because the distributor's delivery driver stayed on-site for 30 minutes to help unload and unpack the equipment. To correct the financial records