Multiple Choice

You have just secured a contract for a commercial project that will require 15,000 feet of steel conduit over the next nine months. Your winning bid was calculated using a material cost of $1.60 per foot. To ensure that your profit margin remains protected even if the price of steel increases during construction, which action is most appropriate?