You have secured a $54,000 renovation contract with an expected profit of $11,000. The project requires $16,000 in materials on day one, and your payroll and overhead run $2,000 per week for 9 weeks. Your current business balance is $6,000. Which project plan best protects your company from the cash shortfall during the job?