Fill in the Blank

Your foreman proposes letting the architect find all the defects during the formal walkthrough in order to save your crew's labor hours. You evaluate this as a highly risky and unprofessional strategy, and reject it because the contractor is strictly responsible for performing a ___________ to create the initial punch list before the owner or architect is involved.