Fill in the Blank

A contractor estimated $4,000 in materials for a commercial lighting retrofit. After the job is completed, the job-costing software shows $3,200 in materials charged to the project, suggesting the job came in well under the material budget. However, during a physical inventory count, the contractor discovers that $700 worth of LED troffer panels were pulled from the warehouse for this same project but never logged in the system. After correcting the inventory records and assigning those panel