True/False

An electrical contractor discovers that their physical warehouse count shows 15 fewer smart dimmers than their digital records indicate, representing a discrepancy of $1,500 in materials. If the contractor simply adjusts the digital records down to match the physical count as a general loss without investigating the variance, they risk having inaccurate job-cost reports because those dimmers might have been installed on an active project without being logged, which would make that project's reported profit margin appear higher than it actually is.