Multiple Choice

A contractor is handling a data-center fit-out and wants to avoid tying up cash in stock. The team buys electrical materials only when each phase is about to start. Payroll stays covered, but the job still runs over budget and slips by two weeks waiting for a switchboard shipment. What is the best evaluation of this purchasing approach?