Two electrical contractors are debating the best way to handle materials for a large commercial tenant-improvement project that will take four months. Contractor A says: 'I always buy everything on Day One so I know I've locked in today's prices and nothing will be back-ordered. That way I avoid any job delays.' Contractor B says: 'I schedule material deliveries in phases—only ordering what I need for the next two to three weeks at a time, even though prices might go up a little on later orders.' Which of the following best evaluates these two approaches?