A fellow electrical contractor shows you the cash-flow forecast for their upcoming $600,000 commercial rewiring project with 10% retainage. In the model, each month's full billed amount is listed as expected collectible income for that period. At the very bottom of the spreadsheet, a single note reads: 'Reminder — $60,000 retainage will be collected after final completion.' The contractor feels confident this model will keep them financially prepared. Which of the following best evaluates the critical flaw in this contractor's forecasting approach?