Multiple Choice

A project report shows a finish-device task ran 7.5 hours over budget. The foreman wants estimating software changed so every future bid uses 22 hours for that task. Based on the listed time for 'Parts pickup' and 'Waiting for inspection,' how valid is that recommendation?