Fill in the Blank

You are evaluating a project manager's performance after a job went over budget. The manager argues the estimating team failed because the 'conduit installation' task took 30 hours longer than budgeted. However, upon auditing the logs, you find the crew actually spent those 30 hours driving to the supply house and waiting for the general contractor to clear the work area. To accurately judge whether the estimator or the project manager is at fault, you conclude the timecards are misleading and dictate that such delays must be tracked separately as ____ time.