Multiple Choice

An electrical contractor discovers an undocumented buried steel tank while trenching for a new service line. To avoid a $2,500 daily delay penalty, the contractor takes high-resolution photos, removes the tank immediately, and then sends a formal notice to the owner and architect that same afternoon. Evaluate the effectiveness of this approach in protecting the contractor’s right to a contract adjustment.