Fill in the Blank

An electrical crew uncovers an unexpected, concrete-encased obstruction while trenching. The site foreman proposes immediately breaking through the obstruction to maintain the project schedule, planning to submit a claim for the extra labor later. Upon evaluating this plan against standard contract requirements, the project manager rejects it, determining that doing so would destroy critical evidence needed for a contract adjustment. The manager correctly insists that formal notice must be provided to the owner and architect before the condition is _________.