Multiple Choice

While trenching for underground feeders on a commercial site, an electrical crew strikes an unmarked, concrete-encased duct bank that is not shown on the site plans. It completely blocks the planned trench path and will require significant extra labor to bypass. To properly preserve the right to a contract adjustment, what is the most critical action the contractor must take before the crew takes any further action in that area?