Multiple Choice

An electrical contractor is preparing the final pay application for a commercial renovation with a base contract of $15,000. During the project, they completed $2,500 in extra wiring that was formally approved through signed change orders. They also completed $1,000 in additional circuit work requested verbally by the client’s representative. When the contractor submits a final invoice for $18,500, the client’s accounting department rejects it, stating the amount exceeds the 'reconciled contract sum' of $17,500. Which analysis identifying the root cause of this rejection is most accurate?