Multiple Choice

You are analyzing why your electrical contracting business consistently experiences a 60-day delay in receiving 'retainage' (the final 10% of payment) after jobs are physically finished. Your audit reveals that while the electrical work is completed on time, your office staff typically takes three weeks to track down the required inspection certificates and manufacturer warranties after the final invoice is sent. Which analysis best explains the relationship between this documentation gap and your company's cash flow?