Multiple Choice

An electrical contractor is preparing the handover package for a newly installed backup generator. The project contract specifies that the equipment warranty must begin on the date of the 'Final Inspection,' which occurred on October 12th. However, the manufacturer's warranty certificate included in the crate is blank regarding the start date. How should the contractor handle this certificate to ensure the documentation delivery is professional and compliant?