Multiple Choice

An electrical contractor is preparing the handover package for a newly installed standby generator. The project contract requires a 2-year warranty starting on the date of 'Project Acceptance' (October 1st). However, the manufacturer's warranty certificate included in the documentation states that the 2-year coverage period begins 'on the date of shipment from the factory' (May 1st of the same year).

Analyze the 5-month discrepancy between these two start dates. If the generator suffers a major component failure 21 months after the project was accepted, what is the most likely financial outcome for the contracting business?