Fill in the Blank

While auditing the closeout documentation for a newly installed transfer switch, an electrical contractor evaluates the standard warranty certificate included in the equipment box. It lists a one-year coverage period, but the client’s contract mandated a five-year term. Because handing over incorrect paperwork could leave the contracting business financially responsible for future repairs, the contractor determines the current document is unacceptable and must be replaced with a revised certificate that explicitly matches the project ____________ before delivery to the owner.