An electrical contractor notices that over the past three months, crews have repeatedly stopped mid-job to run to the supply house for materials that were supposedly in stock, and the office has been placing rush orders for wire and fittings that were already sitting on warehouse shelves. The contractor is considering four corrective actions. Which action best addresses the root cause of both problems simultaneously?